Saturday, September 17, 2005

Fire Inspection Postponed

Our fire inspector was unable to make it to our site yesterday. Half of the inspectors were in a class this week, and that left them very short-handed. We expect to see them Monday morning, though.

On the positive side, two of our buildings have completed their final building inspection, and the other two were just waiting on a stretch of sidewalk which we poured yesterday afternoon. The Building inspector promised come by monday morning and sign off on these other two.

We also received results on our water tests that said all our water is clean. We now have water to the buildings, and will have our plumbing inspection as soon as we can get our backflow valves tested and certified monday morning.

This weekend we are cleaning the admin and high school buildings, moving furniture into these buildings, completing the building skirting, and landscaping around the buildings. Thanks to all the moms and dads who are volunteering to do this work!

0 Comments:

Post a Comment

Subscribe to Post Comments [Atom]

<< Home